THE MEADOWS
PHASE 4A SUBDIVISION
-
10,000m3 of topsoil stripping
-
20,000m3 of site grading
-
Over 3km combined of sanitary, storm, and water main installation, some of which ranging over 6m in depth.
-
75 lot services.
THE MEADOWS
PHASE 4B SUBDIVISION
-
5,000m3 of topsoil stripping
-
15,000m3 of site grading
-
2.5 km combined of sanitary, storm, and water main installation, some of which ranging over 6m in depth.
-
69 lot services
THE MEADOWS
PHASE 5A SUBDIVISION
-
8000m3 of topsoil stripping
-
17,000m3 of import site grading
-
1.5km combined of sanitary, storm, and water main installation, some of which ranging over 6m in depth.
-
65 lot services.
CILO APPARTMENT
BUILDING
-
Completed all area grading around the proposed apartment building complete with detail backfill.
Meadows Parkway Water and Sewer
-
Completed large diameter storm and water main installation along Meadows Parkway.
-
This job required us to safely cross a high pressure gas main at great depth.
-
Our competent supervisors and workers safely and efficiently executed this work.
Taylor Street Primary Water Main
-
1050mm Valve Vault installation for the City of Saskatoon.
-
1050mm Water Main Installation.


Meadows Apartment Building
-
250 unit apartment building excavation
-
Grade Beam Excavation
-
Pile Cap Excavation


Rosewood Phase 5C
-
100 Lot Subdivision excavation
-
100,000m3 of excavation